New Showroom In Providence - 2017

New Showroom Providence 2017 IMG_1895 Exposed trench where footing and foundation will be poured.
Exposed trench where footing and foundation will be poured.
1 / 85
New Showroom Providence 2017 IMG_1896 Showroom will be 92 feet wide and 52 feet deep. Note new entrance to existing shop on the right.
Showroom will be 92 feet wide and 52 feet deep. Note new entrance to existing shop on the right.
2 / 85
New Showroom Providence 2017 IMG_5568 The first stage of the "footing" for the foundation is in progress.
The first stage of the "footing" for the foundation is in progress.
3 / 85
New Showroom Provicence 2017 IMG_5564 Steel "rebar" is placed strategically into the cement for strength.
Steel "rebar" is placed strategically into the cement for strength.
4 / 85
New Showroom Provicence 2017 IMG_5557 Cement is poured to the required depth.
Cement is poured to the required depth.
5 / 85
New Showroom Provicence 2017 IMG_5556 Cement is poured to the required depth.
Cement is poured to the required depth.
6 / 85
New Showroom Provicence 2017 IMG_5573 Every corner and crevice needs to be filled.
Every corner and crevice needs to be filled.
7 / 85
New Showroom Provicence 2017 IMG_5559 Coarse grading (in the foreground) is followed by manual troweling.
Coarse grading (in the foreground) is followed by manual troweling.
8 / 85
New Showroom Provicence 2017 IMG_5561 Thousands of pounds of steel "rebar" are needed.
Thousands of pounds of steel "rebar" are needed.
9 / 85
New Showroom Provicence 2017 IMG_5570 Foundation almost done.
Foundation almost done.
10 / 85
New Showroom Provicence 2017 IMG_5572 Now, let it "set".
Now, let it "set".
11 / 85
New Showroom Provicence 2017 IMG_5581 Prefabricated wooden forms arrive.
Prefabricated wooden forms arrive.
12 / 85
New Showroom Provicence 2017 IMG_5586 Erect the forms.
Erect the forms.
13 / 85
New Showroom Provicence 2017 IMG_5589 Four-foot vertical forms in place on top of footing for foundation wall.
Four-foot vertical forms in place on top of footing for foundation wall.
14 / 85
New Showroom Providence 2017 IMG_1917 Forms securely braced to withstand pressure from tons of wet cement.
Forms securely braced to withstand pressure from tons of wet cement.
15 / 85
New Showroom Provicence 2017 IMG_1918 We are ready for the cement pour.
We are ready for the cement pour.
16 / 85
New Showroom Provicence 2017 IMG_5602 Cement pour begins on the upright wall.
Cement pour begins on the upright wall.
17 / 85
New Showroom Provicence 2017 IMG_5606 Troweling must be done simultaneously with the pour.
Troweling must be done simultaneously with the pour.
18 / 85
New Showroom Provicence 2017 IMG_5613 The second truck arrives with another eleven cubic yards of cement.
The second truck arrives with another eleven cubic yards of cement.
19 / 85
New Showroom Provicence 2017 IMG_5616 The upright forms are removed exposing the finished wall.
The upright forms are removed exposing the finished wall.
20 / 85
New Showroom Provicence 2017 IMG 5618
The forms are loaded back onto the truck to be used on the next job.
21 / 85
New Showroom Provicence 2017 IMG 5885
View from the pit showing the footing and upright finished wall.
22 / 85
New Showroom Provicence 2017 IMG 5886
Another view from the pit showing the footing and upright finished wall.
23 / 85
New Showroom Provicence 2017 IMG 5902
Four inch thick Styrofoam panels are now required by the building code as insulation.
24 / 85
New Showroom Provicence 2017 IMG 5903
Four inch thick Styrofoam panels are now required by the building code as insulation.
25 / 85
New Showroom Provicence 2017 IMG 5904
Four inch thick Styrofoam panels are now required by the building code as insulation.
26 / 85
New Showroom Provicence 2017 IMG 5907
The backfilling and grading begins.
27 / 85
New Showroom Provicence 2017 IMG 5908
The backfilling and grading begins.
28 / 85
New Showroom Provicence 2017 IMG 5910
The backfilling and grading begins.
29 / 85
New Showroom Provicence 2017 IMG 5961
Heavy debris is separated from the backfill material.
30 / 85
New Showroom Provicence 2017 IMG 5959
A heavy roller is used to compact the soil.
31 / 85
New Showroom Provicence 2017 IMG 5962
A heavy roller is used to compact the soil.
32 / 85
New Showroom Provicence 2017 IMG 5987
Back wall footing and foundation is complete.
33 / 85
New Showroom Provicence 2017 IMG 5989
Back wall footing and foundation is complete.
34 / 85
New Showroom Provicence 2017 IMG 5997
With the complete foundation finished, the backfill and final grading is underway.
35 / 85
New Showroom Provicence 2017 IMG 5996
With the complete foundation finished, the backfill and final grading is underway.
36 / 85
New Showroom Provicence 2017 IMG 6011
Backfill and final grading are complete. Construction of the building can now begin.
37 / 85
IMG 6066
Vertical steel columns being placed.
38 / 85
New Showroom Providence 2017 IMG 6063
Horizontal beams in place.
39 / 85
New Showroom Providence 2017 IMG 6065
We can now begin to see the actual shape and size of the structure.
40 / 85
New Showroom Provicence 2017 IMG 6105
Horizontal and vertical beams being put into place.
41 / 85
New Showroom Provicence 2017 IMG 6106
Horizontal and vertical beams being put into place.
42 / 85
New Showroom Provicence 2017 IMG 6107
Horizontal and vertical beams being put into place.
43 / 85
New Showroom Provicence 2017 IMG 6109
The first exterior panel is put into place.
44 / 85
New Showroom Provicence 2017 IMG 6173
Exterior walls are finally in place.
45 / 85
New Showroom Provicence 2017 IMG 6174
View of interior walls.
46 / 85
New Showroom Provicence 2017 IMG 6175
View of interior walls.
47 / 85
New Showroom Provicence 2017 IMG 6176
Second Exterior door is installed.
48 / 85
New Showroom Provicence 2017 IMG 6188
Roof liner is being installed.
49 / 85
New Showroom Provicence 2017 IMG 6195
Exterior view of vertical panels are in place.
50 / 85
New Showroom Provicence 2017 IMG 6212
Exterior roof panels and insulation are being installed.
51 / 85
New Showroom Provicence 2017 IMG 6216
Exterior roof panels and insulation are being installed.
52 / 85
New Showroom Provicence 2017 IMG 6232
Exterior view of the completed roof.
53 / 85
New Showroom Provicence 2017 IMG 6234
Exterior view of the completed roof.
54 / 85
New Showroom Providence 2017 IMG 6315
Mixers lining up with cement for interior floor.
55 / 85
New Showroom Providence 2017 IMG 6318
Chuting cement for interior floor.
56 / 85
New Showroom Providence 2017 IMG 6290
The display area of the interior building space has finally reached the cement pour stage.
57 / 85
New Showroom Providence 2017 IMG 6291
The display area of the interior building space has finally reached the cement pour stage.
58 / 85
New Showroom Providence 2017 IMG 6295
The display area of the interior building space has finally reached the cement pour stage.
59 / 85
New Showroom Providence 2017 IMG 6300
The display area of the interior building space has finally reached the cement pour stage.
60 / 85
New Showroom Providence 2017 IMG 6312
The display area of the interior building space has finally reached the cement pour stage.
61 / 85
New Showroom Providence 2017 IMG 6320
The display area of the interior building space has finally reached the cement pour stage.
62 / 85
New Showroom Providence 2017 IMG 6325
The display area of the interior building space has finally reached the cement pour stage.
63 / 85
New Showroom Providence 2017 IMG 6350
Now that the cement floor has been poured, a sealer must be applied.
64 / 85
New Showroom Providence 2017 IMG 6351
A great photo showing the sealed half and the non sealed half.
65 / 85
New Showroom Providence 2017 IMG 6356
The giant overhead door can be installed now that the cement floor has been completed.
66 / 85
New Showroom Providence 2017 IMG 6374
The glass company arrives to do the exterior framing.
67 / 85
New Showroom Providence 2017 IMG 6373
Exterior framing being completed.
68 / 85
New Showroom Providence 2017 IMG 6419
Wood framing of platform and hallway exit.
69 / 85
New Showroom Providence 2017 IMG 6420
View of completed overhead door and the wood frame material that will be used for the platform and hallway from second floor exit.
70 / 85
New Showroom Providence 2017 IMG 6417
Studs erected for second floor hallway egress.
71 / 85
New Showroom Providence 2017 IMG 6418
Studs erected for second floor hallway egress.
72 / 85
New Showroom Providence 2017 IMG 6927
First electric show room light is in place
73 / 85
New Showroom Providence 2017 IMG 6934
Electric service is near completion
74 / 85
New Showroom Providence 2017 IMG 6935
Sprinkler system being sorted out for installation.
75 / 85
New Showroom Providence 2017 IMG 6936
Sprinkler system being sorted out for installation.
76 / 85
New Showroom Providence 2017 IMG 6369
77 / 85
New Showroom Providence 2017 IMG 6370
78 / 85
New Showroom Providence 2017 IMG 6371
79 / 85
New Showroom Providence 2017 IMG 6372
80 / 85
New Showroom Providence 2017 IMG 6373 (2)
81 / 85
New Showroom Providence 2017 IMG 6374 (2)
82 / 85
New Showroom Providence 2017 IMG 6376
83 / 85
New Showroom Providence 2017 IMG 6405
84 / 85
New Showroom Providence 2017 IMG 6406
85 / 85